Permits are required to build, erect, alter, replace, operate, use or maintain existing point sources of water pollution. A master general permit is one permit issued to multiple locations where activities are similar enough to be covered by a single set of requirements. However, most wastewater permits are site-specific, meaning one permit is issued to one location to reflect the unique nature of that specific wastewater, stormwater or the receiving water. 

As a permit nears its expiration, it is redrafted, modified if needed and made available for public review and comment. The department reviews all public comments before making a decision about the permit. 

If a permittee submits a timely and sufficient application to renew a permit and, through no fault of the permittee, the department is unable to issue the renewed permit before the current permit expires, Code of State Regulations 10 CSR 20-6.015(10)(C) allows the permit to be administratively continued. The terms and conditions of the expired permit remain in effect until the department issues or denies the permit renewal. 

Currently Effective Permits

The following table contains electronic copies of all currently effective site-specific wastewater permits — not master general permits — issued by the department. This includes Concentrated Animal Feeding Operation (CAFO) permits, stormwater permits, wastewater permits and underground injection control well permits. These facilities have been authorized to either discharge to waters of the state, or to operate a no-discharge wastewater treatment facility. The department adds each site specific wastewater permit as it is issued. 

To sort the table below by field, click on the column headings in the table. You can also enter criteria in the search boxes to search for a specific wastewater permit. If you cannot find the information you are looking for, please submit an Open Records/ Sunshine Law Request.

*This is an "and" type search. All search criteria you enter must be met for the permit to appear in the results. If the permit you are searching for is not listed in the results, try again using less criteria.

Effective Date Between
Permit Number Applicant/ Facility County Effective Date Expiration Date Type
MOGC00835 West Plains Sewer Relocation Howell Construction
MOGC00818 Perryville Southeast Wastewater Treatment Plant Perry Construction
MO0135950 Aerospace Composites Center LLC St. Louis Operating
MO0004812 Ameren Missouri-Labadie Energy Center Franklin Operating
MO0140503 American Foods Development Co. LLC Warren Operating
MO0120871 Briarwood Estates Wastewater Treatment Facility Jefferson Operating
MO0140686 Buckman Site-Hallsville Wastewater Treatment Facility Boone Operating
MO0022861 Campbell Wastewater Treatment Facility Dunklin Operating
MO0137774 Clearwater Cove Young Life Wastewater Treatment Facility Stone Operating
MO0052655 Kahoka Wastewater Treatment Facility Clark Operating
MO0140678 MAWC Cedar Hill Lagoon Biosolids Jefferson Operating
MOGS10654 Waggoner's Rolling Hills Farm LLC Newton Operating
MO0140660 Wheatland Wastewater Treatment Facility Biosolids-Beem Site Hickory Operating
MOGC00798 Bates City Industrial Park Lafayette Construction
MOGC00794 Prairie Grove First Plat Jackson Construction
MOGC00806 Elm Crossing St. Charles Construction
MOGC00825 Meeting Hall for Church of Jesus Christ Cape Girardeau Construction
MOGC00817 Northtown Park Subdivision Phase 2 Christian Construction
CP0002499 Missouri Department of Natural Resources-Weston Bend State Park Platte Construction
CP0002473 Newburg Wastewater Treatment Plant Improvements Phelps Construction
MOGC00788 Arrowhead Lake Estates-Southwest Boone Construction
MOGC00810 Providence Estates Phases 8 and 9 Warren Construction
MOGC00809 Summit Orchards West Jackson Construction
MOGC00808 Utility Relocation-West Highway 54 Camden Construction
MOGC00764 Fitz Ridge Subdivision Greene Construction
MOGC00805 Innsbrook Estates Wastewater Treatment Plant Warren Construction
CP0002477 California South Wastewater Treatment Plant Improvements Moniteau Construction
MOGC00784 Prairie Ridge Phase 1 Greene Construction
MO0042480 Billings Wastewater Treatment Facility Christian Operating
MO0082767 Butterball LLC Jasper Operating
MOGC00819 CIP#6 Lower Brookline and CIP#7 McElhane Greene Construction
MO0135593 Fastlane Taylor Wastewater Treatment Plant Marion Operating
MO0121371 Hunter's Ridge Subdivision Wastewater Treatment Plant St. Francois Operating
MOGC00822 Jackson Drive Industrial Park Jackson Construction
MO0134309 Keystone Estates Wastewater Treatment Plant Lincoln Operating
MOGC00821 Kinder Farms Subdivision Phase 1 Cape Girardeau Construction
MO0099040 Knolls Resort Condominiums Wastewater Treatment Facility Camden Operating
MOGC00820 Meadowbrooke Jackson Construction
MO0040461 Missouri-American Water Co.-Cedar Hill Lagoon Jefferson Operating
MO0129755 Missouri-American Water Company, Purcell Wastewater Treatment Facility Jasper Operating
MOGS10655 Nolt Farms LLC Moniteau Operating
MO0118559 Orchard Farms Apartments Wastewater Treatment Facility St. Charles Operating
MO0117595 Park Place on the Lake Condominiums Wastewater Treatment Plant Camden Operating
MO0118206 Pony Wastewater Treatment Facility, The Butler Operating
MO0110108 Skyhaven Motel and Convenience Store Wastewater Treatment Facility Johnson Operating
MO0081850 Skyline Village Inc. Wastewater Treatment Facility Audrain Operating
MO0102342 Southwood Shores Condominiums Wastewater Treatment Facility Camden Operating
MO0057312 Terre Du Lac South One Cell Lagoon St. Francois Operating
MO0125776 TT Sewer Co. Wastewater Treatment Facility Camden Operating
MO0060101 U.S. Army Corps of Engineers-Cedar Ridge Wastewater Treatment Facility Cedar Operating