Metallic Mineral Waste Management permits are issued to operators by the department under the Metallic Minerals Waste Management Act. The act is a state law with no federal oversight.
Mineral processing wastes are referred to in the federal Resource Conservation and Recovery Act (RCRA) as wastes that are generated during the extraction and beneficiation of ores and minerals and are exempt under RCRA under the Bevill Amendment by the Environmental Protection Agency. These wastes can be subdivided into a number of categories: waste rock, mill tailings, coal refuse, wash slimes and spent oil shale. The mining and processing of mineral ores results in the production of large quantities of residual wastes that are for the most part earth- or rock-like in nature.
Length of Permit
Issued for one year. The permit must be renewed annually until the determination is made that inspection-maintenance is no longer required.
Laws, Rules and Regulations
- Federal Law: Federal Surface Mine Control and Reclamation Act
- State Law: Metallic Minerals Waste Management Act 444.352 to 444.380, RSMo
- State Law: Land Reclamation Act at 444.760 to 444.790, RSMo.
- Code of State Regulations: Division 40 - Missouri Mining Commission, 10 CSR 40
- Commission, Board, Council: Missouri Mining Commission
How to Apply
Applications Applications consist of financial assurance information and detailed waste management area closure and inspection-maintenance plans that must be reviewed and updated every five years. The plans establish and explain the technical steps proposed to accomplish and maintain closure after mining and waste disposal is completed. Issues addressed in the plans include:
During the ongoing permit application review, the program coordinates with the other areas within the department that are involved with the metallic minerals waste management areas. These include the department’s Air Pollution Control Program, Water Protection Program, Waste Management Program, Environmental Remediation Program and Missouri Geological Survey. This coordination process allows other programs to review and comment on the technical aspects of the plans so all environmental issues may be incorporated into the permit. Fees A processing fee of $10,000 shall accompany the filing of the application for a facility or metallic minerals waste management area. An annual fee of $7,500 per facility or metallic minerals waste management are is due when the permit is approved and on each anniversary date thereafter until the determination is made that inspection-maintenance is no longer required. All sums received through the payment of fees or the forfeiture of bonds pursuant to sections 444.352 to 444.380 RSMo will be placed in the state treasury and credited to the "Metallic Minerals Waste Management Fund." Additional, a financial assurance instrument in the amount of $20,000 for the first 20 acres shall be submitted. If the acreage totals more than 20 acres, than an additional $1,000 per acre is required. |
Timeline/ Process
An application, closure plan and inspection-maintenance plan are submitted to the department. Staff review the application packet for completeness. This process can take up to three months, or even longer if necessary. The department will request additional information if the application is not complete, which will delay the review process. During the ongoing permit application review, the program coordinates with the other areas within the department that are involved with the metallic minerals waste management areas. These include the department’s Air Pollution Control Program, Water Protection Program, Waste Management Program, Environmental Remediation Program and Missouri Geological Survey. This coordination process allows other programs to review and comment on the technical aspects of the plans so all environmental issues may be incorporated into the permit. The department staff will provide comments on the application packet to the applicant if necessary. If all comments were addressed satisfactorily, or no additional comments, then the application packet review process is completed. If there are additional comments, another round of comments are made and submitted back to the applicant. The department will continue the process until everything has been fully addressed and answered before a final determination is completed. |
Public Participation
There are no public notification or public participation process involved during this permitting activity. Administrative Hearing Commission Anyone who is adversely affected by the director's decision to issue, deny, suspend or revoke a permit must appeal within 30 days of the decision to the Administrative Hearing Commission as provided by 621.250.3 RSMo. All appeals must be filed by petition and send to: Administrative Hearing Commission |
Requirements
ReportingThe permit holder is required to submit quarterly reports for groundwater monitoring to the department. The purpose of the plan shall be to prevent the contamination of groundwater
The groundwater protection plan preparation, review and implementation shall be Contaminants from metallic minerals waste disposal shall not cause or contribute to the exceedence in aquifers of Missouri’s Water Quality Standards in 10 CSR 20-7.031(5). The director may establish groundwater monitoring compliance points as necessary to achieve this objective. |
Renewal
The department mails an invoice to all permit holders annually to pay their annual operating permit fee. Permittees are also required to submit their groundwater reports by email to the Land Reclamation Program. |
Resources
Inspections and EnforcementInspections are performed semiannually on the 10 metallic minerals waste management permit areas within Missouri. During the course of these inspections, all aspects of each company’s permits are evaluated. The main focus of these inspections is to assess the company's compliance with environmental laws administered by the Missouri Department of Natural Resources. The program is entrusted as the coordinating agency within the department for each active metallic mineral producer currently operating in Missouri. Enforcement under this law is significantly different from enforcement under either the coal or industrial minerals units of the program. If it should become necessary to issue a citation to any of the metal producers, the authority to do so rests solely with the director of the Department of Natural Resources. Enforcement is only authorized by law after attempts to eliminate the violation through conference, conciliation and persuasion have been exercised and exhausted. Additional Permits RequiredAdditional permits that may be required with this permit include: Issued PermitsThe department has issued 10 metallic mineral waste management permits in Missouri. You may access this list by visiting Metallic Mineral Issued Permits. A map of the metallic minerals waste management permitted areas can be accessed by the Industrial and Metallic Mineral Sites map viewer. |