The Missouri Department of Natural Resources describes a Power Plant business as:

An industrial facility that generates power either as electric or nuclear from primary energy.

You may need some or all of the following permits for a Power Plant business:

Air icon
Air Intermediate Operating Permit

If your business is required to obtain a Part 70 Operating Permits but accepts voluntary, practically enforcement limitation to reduce emissions to less than 100 tons per year of any regulated pollutant and is less than 10 tons per year of any single hazardous air pollutant and less than 25 tons per year of any combined hazardous air pollutant, you may require an Air Intermediate Operating Permit to address potential air emissions.

Air icon
Air Major Construction Permit Sections (7), (8) & (9)

If your business plans to construct a new installation or modify an existing minor installation and the project has the potential to emit more than major emission levels of a regulated air containment or construct a new installation or modify an existing major installation and the project has the potential to emit more than the minor levels per year, you may require an Air Major Construction Permit Sections (7), (8) & (9) to address potential air emissions.

Air icon
Air Minor Construction Permit Section (5)

If your business plans to construct a new installation or modify an existing minor installation and the project has the potential to emit less than major source levels per year; or you plan to construct a new installation or modify an existing major installation and the project has the potential to emit less than the minor levels per year, you may require an Air Minor Construction Permit to address potential air emissions.

Air icon
Air Part 70 Operating Permit

If your business has the potential to emit greater than 100 tons per year of any regulated pollutant, has the potential to emit greater than 100 tons per year of any single hazardous air pollutant, or greater than 25 tons per year of combined hazardous air pollutants, or is required by a New Source Performance Standard or a Maximum Achievable Control Technology, you may require an Air Part 70 Operating Permit.

Water icon
Clay Pits Permit MOG840000

If your business operates a clay pit or mine, you must obtain a Clay Pits MOG840000 master general permit for the discharge of stormwater, snowmelt and infiltration water from the site.

Geological Survey Program Contact Us icon
Dam and Reservoir Safety Registration Permit

If you own an existing dam built prior to Aug. 13, 1981 that is 35 feet or more in height, you are required to obtain a Dam and Reservoir Safety Registration Permit.

Waste icon
Hazardous Waste Generator Registration

If you produce or store some form of hazardous waste as a result of your business processes, you may be required to register as a hazardous waste generator.

Waste icon
Hazardous Waste/ Infectious Waste Transporter License

If you or your business plans to transport hazardous waste including waste oil, explosives, gases, flammable and combustible liquids, flammable solids, oxidizers and organic peroxides, poisons, radioactive materials, corrosives or infectious waste, you must obtain a Hazardous/ Infectious Waste Transporter License.

Geological Survey Program Contact Us icon
In-Stream Sand and Gravel Mining Permit

If your business plans to engage in surface mining of industrial minerals such as sand, gravel, limestone, dolomite, clay or other construction aggregates, you may need an Industrial Mineral Mines Permit – In-stream Sand and Gravel Mining to engage in surface mining.

Geological Survey Program Contact Us icon
Open Pit Mining Permit

If your business plans to remove topsoil and other soil material to expose the mineral commodity, you may need an Industrial Minerals Mines Permit - Open Pit Mining. Industrial mineral open pit mine sites range in size from one acre sand and gravel pits to 1,000 acre limestone sites.

Water icon
Public Drinking Water Construction Permit

If your business plans to construct a public water system that will supply drinking water to the public, you must obtain a Public Drinking Water Construction Permit. You must obtain this permit if you also plan to complete the following construction projects to the water system: waterline extensions, waterline replacements, drilling water supply well, construction a storage tank, adding a disinfection system, treatment changes, building a pump station or other improvements or modifications. A public water system has at least 15 service connections or serves at least 25 people at least 60 days out of the year. If your business plans to connect to a permitted public water system, then you are not required to obtain this permit.

Water icon
Public Drinking Water Permit to Dispense

If your business plans to operate a public water system that supplies drinking water to the public, you must obtain a Public Drinking Water Permit to Dispense. A public water system has at least 15 service connections or serves at least 25 people at least 60 days out of the year. If your business plans to connect to a permitted public water system, then you are not required to obtain this permit.

Waste icon
Remedial Action Plan

If you want to treat, store or dispose of hazardous remediation waste at a remediation waste management site in Missouri, you may be required to follow a Remedial Action Plan. The plan lists conditions about how to treat, store or dispose of hazardous remediation waste.

Waste icon
Solid Waste Processing Facility Construction Permit

If your business plans to build a facility where solid wastes are transferred from one container to another or are processed, you are required to apply for a Solid Waste Processing Facility Construction Permit. Types of processing facilities include incinerator, compost plant, infectious waste, transfer station and material recovery, with or without composting.

Waste icon
Solid Waste Processing Facility Operating Permit

If your business plans to operate a facility where solid wastes are transferred from one container to another or are processed, you are required to apply for a Solid Waste Processing Facility Operating Permit. Types of processing facilities include incinerator, compost plant, infectious waste, transfer station and material recovery, with or without composting.

Waste icon
Underground Petroleum Storage Tank Registration

If your business includes an underground storage tank on the property used to store either petroleum or certain hazardous substances, or if you plan to have a tank installed for these reasons, you may be required to submit an Underground Storage Tank Registration with the department.