PUB 541 - Permit Transfer Requirements Tables

Department of Natural Resources fact sheet
12/2017
Department of Natural Resources Director: Carol S. Comer
PUB541permitreqs

Air Pollution Control Program (APCP) Permit Transfer Requirements Table

Transfer Requirements APCP Construction Permit APCP Operating Permit APCP Open Burning Permit
Permit Transferable Yes Yes No
Forms and Other Information Required Letter of Notification Letter of Notification  
Inspection Required No No  
Public Participation Required No No  
Fees Required No No  
Transfer Time Frame Upon receipt of complete transfer information Upon receipt of complete transfer information  
Regulation or Law Cite for Transfer 10 CSR 10-6.060 10 CSR 10-6.065  
Program Contact Construction Permit Unit, APCP, 573-751-4817 Operating Permit Unit, APCP, 573-751-4817 Regional Offices - See the regional office map for offices in your area

Hazardous Waste Program (HWP) Permit Transfer Requirements Table

Transfer Requirements HWP Hazardous Waste Management Facility Permit HWP Hazardous Waste Resource Recovery Certification HWP PCB Facility Permit HWP Hazardous Waste Generator Registration HWP Hazardous Waste Transporter License
Permit Transferable Yes Yes Yes Yes No
Forms and Other Information Required

Revised permit application at dnr.mo.gov/forms/HWFacPermitApp.pdf or epa.gov/epaoswer/hazwaste/data/form8700/forms.htm.
Includes violation history and financial assurance.

Written request 60 days prior to change. May require financial assurance.

Revised permit application. dnr.mo.gov/forms/780-1897.pdf. Includes violation history and financial assurance.

Notification of Requested Waste Activity Form: MO 780-1164 dnr.mo.gov/forms/780-1164-f.pdf

 
Inspection Required No No No No  
Public Participation Required Facility must notify those on the facility mailing list. No Facility must notify those on the facility mailing list. No  
Fees Required No No No $100 registration fee for new registrations or reactivation  
Transfer Time Frame 90 days prior to change 60 days 90 days prior to change 7 days  
Regulation or Law Cite for Transfer 10 CSR 25-7.270
40 CFR 270.40
10 CSR 25-9.020
(3)(E)1
10 CSR 25-7.270
40 CFR 270.40
10 CSR 25-5.262 (2)(A)  
Program Contact Permits Section, HWP, 573-751-3553 Permits Section, HWP, 573-751-3553 Permits Section, HWP, 573-751-3553 Budget and Planning Section, HWP, 573-751-3176  
Notes Change of ownership is a Class 1 permit modification with prior director approval   Change of ownership is a Class 1 permit modification with prior director approval    

Solid Waste Management Program (SWMP) Permit Transfer Requirements Table

Transfer Requirements SWMP Solid Waste Disposal Area Permit SWMP Solid Waste Processing Facility Permit SWMP Infectious Waste Processing Facility Permit SWMP Scrap Tire Site Permits and Processing Facility SWMP Scrap Tire Hauler Permit
Permit Transferable Yes Yes Yes No No
Forms and Other Information Required Information on transfer of ownership
Violation Disclosure Statement
Updated Operation and design plans
A financial assurance instrument
Information on transfer of ownership
Violation Disclosure Statement
Updated Operation and design plans
Information on transfer of ownership
Violation Disclosure Statement
Updated Operation and design plans
   
Inspection Required No No No    
Public Participation Required No No No    
Fees Required No No No    
Transfer Time Frame 6 months 6 months 6 months    
Regulation or Law Cite for Transfer Section 260.205.17
RSMo. (Senate Bill 60)
Section 260.205.17
RSMo. (Senate Bill 60)
Section 260.205.17
RSMo. (Senate Bill 60)
   
Program Contact Engineering Section, SWMP, 573-751-5401 Engineering Section, SWMP, 573-751-5401 Engineering Section, SWMP, 573-751-5401 Enforcement Section, SWMP, 573-751-5401 MoDOT, Motor Carrier Services, 573-751-3358

Water Pollution Control Branch

Transfer Requirements WPCB Operating Permit WPCB General Permit WPCB Construction Permit WPCB 404/401 Certification
Permit Transferable Yes Yes* Yes  
Forms and Other Information Required Information on transfer of ownership
Transfer of Operating Permit
Information on transfer of ownership
Transfer of Operating Permit

Information on transfer of ownership. Application for Transfer of Construction Permit

 
Inspection Required No No No  
Public Participation Required No No No  
Fees Required Yes Yes Yes  
Transfer Time Frame <1 Month <1 Month <1 Month  
Regulation or Law Cite for Transfer Section 644.051.9
RSMo.
Section 644.051.9
RSMo.
Section 644.051.9
RSMo.
 
Program Contact Operating Permits Section, WPCB, 573-751-1300 Applicable MoDNR regional office. ** Engineering Section, WPCB, 573-751-1300 Operating Permits Section, WPCB, 573-526-1300
* Land disturbance permits (MORA and MOR100) are not transferable.
** See regional offices map

Water Resources Center (WRC) Permit Transfer Requirements Table

Transfer Requirements WRC Dam and Reservoir Safety Permits
Permit Transferable Yes
Forms and Other Information Required Letter of Notification requested
Inspection Required No
Public Participation Required No
Fees Required No
Transfer Time Frame Immediately upon receipt of request to transfer from the seller to the buyer
Regulation or Law Cite for Transfer 10 CSR 22-2.090
Program Contact Dam and Reservoir Safety, 573-368-2175
Notes The permit holder of record will be held responsible for maintaining compliance