Updated March 23, 2017

 

Air Monitoring

Feb. 23, 2017 -- Daily Results -- Air monitoring activities continue as the department collects data via our AreaRAE system on a 24 hour per day/7 day per week basis. Daily monitoring events by the department continue to be completed twice per day on a scheduled path.

newFeb. 20 - Feb. 23, 2017

newFeb. 16 - Feb. 20, 2017

newFeb. 13 - Feb. 16, 2017

Feb. 9 - Feb. 13, 2017

Feb. 6 - Feb. 9, 2017

Feb. 2 - Feb. 6, 2017

Jan. 30 - Feb. 2, 2017

Jan. 26 - Jan. 30, 2017

Jan. 23 - Jan. 26, 2017

Jan. 19 - Jan. 23, 2017

Jan. 16 - Jan. 19, 2017

Jan. 12 - Jan. 16, 2017

 

Air Sampling

Jan. 4, 2017 -- Weekly and Monthly Results -- Air sampling activities continue on a weekly basis by the department and total reduced sulfur sampling occurs on a monthly basis.

newDec. 28, 2016 - Weekly Air Sampling

newDec. 21, 2016 - Weekly Air Sampling

newDec. 13, 2016 - Weekly Air Sampling

newDec. 7, 2016 - Monthly Air Sampling for Total Reduced Sulfur Compounds

newDec. 6, 2016 - Weekly Air Sampling

newNov. 29, 2016 - Weekly Air Sampling

newNov. 21, 2016 - Weekly Air Sampling

Nov. 15, 2016 - Weekly Air Sampling

Nov. 8, 2016 - Weekly Air Sampling

Nov. 2, 2016 - Weekly Air Sampling

Nov. 1, 2016 - Monthly Air Sampling for Total Reduced Sulfur Compounds


First Agreed Order (13SL-CC01088) Compliance Reporting

Reports submitted by Republic Services for Bridgeton Landfill:

Jan. 27, 2017 -- Republic Services submitted for Bridgeton Landfill the following reports:

Sept. 30, 2016 -- Republic Services submitted the Bridgeton Landfill Gas Corrective Action Update as required for compliance with the First Agreed Order

Quarterly (To be filed with the department within 30 days after the last day of each quarter)

As-built drawings of infrastructure changes since previous quarterly submittal, if any.

Weekly Reporting

Weekly Data Submittals are required to be submitted by Bridgeton Landfill to the department and include:

Monthly Reporting

Facility Status Report required to be submitted to the Court by Republic Services.

Monthly Data Submittals to the department are required to include:

Neck Heat Extraction System Monthly Report -- As required per the department’s Dec. 4, 2015 approval letter for the November 2015 Technical Evaluation of the Heat Extraction Barrier and as incorporated into the EPA’s April 28, 2016 Administrative Settlement Agreement and Order on Consent for Removal Actions (ASAOC), Bridgeton Landfill shall submit a monthly report to the department on the operation and effectiveness of the heat extraction barrier

Neck Heat Extractions System As-Built Drawings

Inert Gas Injection Reports

Groundwater Reports

Other Reports
  • newDecember 2016 -- Bridgeton Landfill submitted as-built drawings for temperature monitoring probe installation in the North Quarry. View the drawings. (01/06/07)
  • Oct. 20, 2016 -- Bridgeton Landfill submitted the facility's update to the Heat Removal Pilot Study. View the quarterly report. (10/27/16)