Updated May 24, 2016

 

Air Monitoring

May 5, 2016 -- Daily Results -- Air monitoring activities continue as the department collects data via our AreaRAE system on a 24 hour per day/7 day per week basis.  Daily monitoring events by the department continue to be completed twice per day on a scheduled path.

newMay 2 - 5, 2016

newApril 28 - May 2, 2016

newApril 25 - 28, 2016

April 21 - 25, 2016

April 18 - 21, 2016

April 14 - 18, 2016

April 11 - 14, 2016

April 7 - 11, 2016

April 4 - 7, 2016

March 31 - April 4, 2016

 

Air Sampling

April 12, 2016 -- Weekly and Monthly Results-- Air sampling activities continue on a weekly basis by the department and total reduced sulfur sampling occurs on a monthly basis.

newApril 5, 2016 - Weekly Air Sampling

newMarch 29, 2016 - Weekly Air Sampling

March 22, 2016 - Weekly Air Sampling

March 17, 2016 - Weekly Air Sampling

March 7, 2016 - Weekly Air Sampling

March 2, 2016 - Weekly Air Sampling

Monthly Air Sampling for Total Reduced Sulfur Compounds

 

First Agreed Order (13SL-CC01088) Compliance Reporting

Reports submitted by Republic Services for Bridgeton Landfill:

newApril 27, 2016 -- Republic Services submitted for Bridgeton Landfill the following reports:

Jan. 30, 2016 -- Republic Services submitted for Bridgeton Landfill the following reports:

Jan. 18, 2016 -- Republic Services submitted the Bridgeton Landfill Gas Corrective Action Update as required for compliance with the First Agreed Order

Quarterly (To be filed with the department within 30 days after the last day of each quarter)

As-built drawings of infrastructure changes since previous quarterly submittal, if any.

Weekly Reporting

Weekly Data Submittals are required to be submitted by Bridgeton Landfill to the department and include:

Monthly Reporting

Facility Status Report required to be submitted to the Court by Republic Services.

Monthly Data Submittals to the department are required to include:

Other Reports

newNov. 4-5, 2015 -- Bridgeton/West Lake Landfill Radiological Air Sampling Report. View report. (05/19/16)

April 26, 2016 -- Comprehensive Sampling Results July 2015 and October 2015. View report. (04/29/16)

March 16, 2016 -- The department issued a letter to the Bridgeton Landfill regarding its financial assurance, closure, post-closure and corrective action plans. View the letter. (03/17/16)

Jan. 27, 2016 -- The department responded to the Bridgeton Landfill's North Quarry Cap Enhancements Workplan and Schedule. View the letter.

Jan. 27, 2016 -- The department responded to the Bridgeton Landfill's Gas Interceptor Trench Proposed Modifications. View the letter.

Jan. 27, 2016 -- Bridgeton Landfill's contractor submitted the Fourth Quarter 2015 Groundwater Assessment Summary Report. View the summary report.

Jan. 24, 2016 -- Bridgeton Landfill submitted the facility's Update to the Heat Removal System Pilot Study. View the update

Dec. 7, 2015 -- The department responded to Bridgeton Landfill's "December 2015 Landfill Gas Enhancement" submittals. View the letter.

Dec. 4, 2015 -- The department responded to the Bridgeton Landfill's Neck Area Heat Extraction Barrier evaluation. View the letter.